The following labor standards have been established for a particular product:
Standard labor-hours per unit of output 9.8 hours
Standard labor rate $13.60 per hour
The following data pertain to operations concerning the product for the last month:
Actual hours worked 7,600 hours
Actual total labor cost $100,320
Actual output 950 units

What is the labor efficiency variance for the month?