Kapoor Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products.

Activity Cost Pools Activity Rate
Setting up batches $ 95.45 per batch
Assembling products $ 8.75 per assembly hour
Processing customers orders $ 51.38 per customer order

Data concerning two products appear below:

Product J00A Product S06U
Number of batches 37 46
Number of assembly hours 177 895
Number of customer orders 20 39

Required:
a.

How much overhead cost would be assigned to Product J00A using the company’s activity-based costing system? (Round your answer to 2 decimal places. Omit the “$” sign in your response.)

Total overhead cost $

b.

How much overhead cost would be assigned to Product S06U using the company’s activity-based costing system?(Round your answer to 2 decimal places. Omit the “$” sign in your response.)

Total overhead cost

$